Scroll Top
North Dakota | Montana | South Dakota | Minnesota | Wyoming

Mitchell, Water Tower, & Jaycee Pool

Mitchell, Water Tower, & Jaycee Pool

Great Falls, Montana

Interstate Engineering recommended a complete rehabilitation of Mitchell Pool, including new stainless-steel gutters, PVC liners, updated filtration systems, new concrete decks, and modernized electrical and mechanical systems, which would bring the pool up to code and reduce operating costs. For Water Tower and Jaycee Pools, recommendations included new filtration systems, gutters, deck equipment, electrical work, and bathhouse renovations, addressing issues like deteriorated gutters, spalling walls, and outdated re-circulating systems.

The community swimming pools in Great Falls were built and renovated in the 1960s. Because the pools’ systems and infrastructures had deteriorated over time, the city faced significant capital and maintenance issues. The city retained Interstate Engineering’s services to evaluate all three swimming pool complexes and develop a list of alternatives ranging from closing to complete replacement. The study prepared by Interstate Engineering resulted in the following recommendations:

Mitchell Pool: Complete rehabilitation was warranted, which included a new stainless steel gutter system, pool floor, and wall rehabilitation by installing a PVC liner system, filtration/recirculation system, new concrete decks, new electrical/mechanical systems, new filter room, pool heater, and backwash balance tank systems. The improvements brought the Mitchell Pool up to the current codes and decreased the chemical, natural gas, and electrical costs.

Water Tower and Jaycee Pools: Both pools had deteriorated gutter systems with broken grate tiles, plaster spalling of the pool tank walls, heaving concrete decks, outdated and inefficient pool heaters, re-circulating pumps and systems were at the end of their useful life, restrooms were not ADA accessible, and the dressing rooms needed to be renovated. Improvements to each facility included a new filtration/recirculation system, a new stainless steel gutter, chemical feed rehabilitation, new concrete deck and fencing, pool floor and wall rehabilitation using a PVC liner, new deck equipment, electrical work, and bathhouse rehabilitation.

The rehabilitation project was estimated to cost just under $2.3 million. General Obligation Bond financing in the entire amount for a ten-year term was placed on the November 7, 2006, ballot. Interstate Engineering prepared informational packets to inform the electorate, including drawings and cost estimates. The general obligation bond passed with 15,158 votes to approve the bonds and 5,648 votes against approval. On December 19, 2006, the city commission approved the professional services agreement with Interstate Engineering to rehabilitate the Mitchell, Water Tower, and Jaycee Pools.

The decision was later made to pursue funding and construction of spray parks/splash decks for the community. Interstate Engineering was retained to evaluate the potential location of a single splash deck complex or several smaller facilities. It was determined that the best alternative was two locations, one at Jaycee and the other at Water Tower Pool, thereby creating an aquatics complex at each location and expanding entertainment for the community at locations on either side of the city. Although funding was different for the two projects, for efficiency and cost savings, both projects were bid together and constructed simultaneously.

Mitchell final 2
Interstate Engineering Team

Brian Milne, PE – Project Engineer, Project Manager

COMPLETION DATE
  • November 2008