Beulah Main Street

Main Street Project Notes: April 12

The contractor began milling the asphalt roadway surface within the project area on Friday, April 12. Temporary water services will be hooked up and installed by Wednesday, April 17. Stage 1 and Stage 2 work areas will be closed off starting Monday, April 15, until the work is completed within those two stage areas. The rest of Main Street will be open to the public until Stages 1 and 2 are completed. Stages 1 and 2 are expected to be complete by June 17.