The intersection of 1st Avenue East will be closed through July 22 unless work is finished earlier. It will be opened to the public as soon as possible.
Beulah Main Street
Areas of town will be without water from 8 am to 3 pm while the construction crew replaces a water main valve on the project. Impacted areas will include the entire east end of Main Street east of 2nd Ave NE, and from Main Street to 2nd Street NE. It is not anticipated that the shutdown will extend beyond the areas shown in the attached map – streets highlighted in red are the impacted areas for the water shutdown. While we do not anticipate the shutdown extending beyond the areas shown, it is possible that further areas may be affected if existing water valves do not perform adequately and isolate the work area.
PUBLIC MEETING NOTICE
July 8 & July 22
11am – Noon
Joy Fitness Building, Main Street, Beulah
The public and business owners are invited to ask questions about the construction activities and overall project.
PUBLIC MEETING NOTICE
June 24 @ 11AM
The public meeting scheduled for Monday, the 24th, will be held at the In Joy Fitness building. Access to the building will be made available from the rear, at the doorway in the alleyway. Signage will be provided to help guide the public to the correct door for the meeting. Thank you for your continued cooperation during these construction operations, and we look forward to visiting with any businesses or the public regarding the project.
STAGES 1-3 STATUS UPDATE (CONSTRUCTION OPERATIONS)
Last week, the contractor worked on sanitary sewer piping installation and sanitary service installation in stage 3. In stages 1 & 2 concrete work continued with parking lanes and sidewalks. This week, the contractor will be working on the following:
1. Sanitary service installations in stage 3 & 4.
2. Water main installation in stage 3 & 4.
3. Water services in stage 3.
4. Begin storm sewer installation in stage 3
5. Continue concrete installation in stages 1 & 2.
STAGES 1-3 STATUS UPDATE (CONSTRUCTION OPERATIONS)
Last week, the contractor worked on sanitary sewer piping installation and sanitary manhole installation in stage 3. In stages 1 & 2, concrete work was continued with aprons and valley gutters. This week, the contractor will be working on the following:
1. Sanitary service installation in stage 3.
2. Water main installation in stage 3.
3. Water services in stage 3.
4. Continue concrete installation in stages 1 & 2.
5. Continue electrical installation in stages 1 & 2.
Public Notice
Please remember that while the project is ongoing, personnel are requested to stay out of the construction area at all times except for in the pedestrian channelization areas. We appreciate your cooperation and understanding during this project, and with your support, we look forward to the safe and successful completion of these city improvements.
PUBLIC MEETING NOTICE
June 10 & June 24
11am – Noon
Joy Fitness Building, Main Street, Beulah
The public and business owners are invited to ask questions about the construction activities and overall project.
CONSTRUCTION UPDATE
Last week, the contractor worked on removals in Stage 3, completed a water valve replacement on 2nd Avenue NE, and placed Class 5 aggregate on Stages 1 and 2. This week, the contractor will be working on the following:
Removals on Main Street between Central Avenue and 1st Avenue E.
Sanitary sewer replacement in Stage 3 to 1st Avenue E.
Curb and Gutter placement in Stages 1 & 2.
Sidewalk placement in Stages 1 & 2
Areas of town will be without water from 8 am to 3 pm while the construction crew replaces a water main valve on the project. Impacted areas will include 1st Ave NE from Central Ave E to 2nd St NE. It is not anticipated that the shutdown will extend beyond the areas shown in the attached map – streets highlighted in red are the impacted areas for the water shutdown. While we do not anticipate the shutdown extending beyond the areas shown, it is possible that further areas may be impacted in the event that existing water valves do not perform adequately and isolate the work area.
NOTICE: Should the necessary water valves not hold for this temporary shutdown as expected, further isolation attempts would be required and may result in water loss for a much larger area. Due to the layout of the valves within town, it is possible that all areas from 3rd Street North down to the railroad tracks may be without water during this timeframe.