Main Street Project Notes: June 19

Stages 1-3 Status Update (Construction Operations)

Last week, the contractor worked on sanitary sewer piping installation and sanitary service installation in stage 3. In stages 1 & 2 concrete work continued with parking lanes and sidewalks. This week, the contractor will be working on the following:

  1. Sanitary service installations in stage 3 & 4.
  2. Water main installation in stage 3 & 4.
  3. Water services in stage 3.
  4. Begin storm sewer installation in stage 3
  5. Continue concrete installation in stages 1 & 2.