Main Street Project Notes: Stage 1 & 2 Status Update (Construction Operations)

Stage 1 & 2 Status Update (Construction Operations)

Last week, the contractor finished installing perimeter gate valves on the water main and has now begun installing sanitary sewer main on the project. This week, old manholes are being taken out and new manholes are being installed in place. Once the manholes are installed, the contractor will install sanitary sewer main between the manholes and tie the system together. After the contractor finishes installing sanitary sewer main, then they will begin to install water main and storm sewer main within the project area.