Main Street Project Notes: May 29

Construction Update

Last week, the contractor worked on grading Stages 1 & 2 as well as moving the temp water system. The subcontractor worked on the electrical system for the streetlights and power to the tree locations. This week, the contractor will be working on the following:

  1. Removing concrete in front of Bronson’s Supervalu.
  2. Grading Stages 1 & 2.
  3. Placing Class 5 on Stages 1 & 2.
  4. Beginning removals in Stage 3.