Main Street Project Notes: June 3

Construction Update

Last week, the contractor worked on removals in Stage 3, completed a water valve replacement on 2nd Avenue NE, and placed Class 5 aggregate on Stages 1 and 2. This week, the contractor will be working on the following:

  1. Removals on Main Street between Central Avenue and 1st Avenue E.
  2. Sanitary sewer replacement in Stage 3 to 1st Avenue E.
  3. Curb and Gutter placement in Stages 1 & 2.
  4. Sidewalk placement in Stages 1 & 2