Main Street Project Notes: June 10
Stages 1-3 Status Update (Construction Operations)
Last week, the contractor worked on sanitary sewer piping installation and sanitary manhole installation in stage 3. In stages 1 & 2, concrete work was continued with aprons and valley gutters. This week, the contractor will be working on the following:
- Sanitary service installation in stage 3.
- Water main installation in stage 3.
- Water services in stage 3.
- Continue concrete installation in stages 1 & 2.
- Continue electrical installation in stages 1 & 2.