Main Street Project Notes: June 19
Stages 1-3 Status Update (Construction Operations)
Last week, the contractor worked on sanitary sewer piping installation and sanitary service installation in stage 3. In stages 1 & 2 concrete work continued with parking lanes and sidewalks. This week, the contractor will be working on the following:
- Sanitary service installations in stage 3 & 4.
- Water main installation in stage 3 & 4.
- Water services in stage 3.
- Begin storm sewer installation in stage 3
- Continue concrete installation in stages 1 & 2.